Questions and answers

Using Kokkola Arena.

Does the arena have a running track around it?

A four-lane running track more than 270 metres long runs around the arena on the ground floor. The track allows middle- and long-distance running training and indoor competitions. In addition to running, the track serves as a cycling training track, a fitness testing track, a warm-up track and a space for school PE. The straight on the Kaarlelankatu side forms a six-lane 60-metre sprint straight with safety zones, where indoor sprinting can be trained and competed. The only competition events not possible are the steeplechase with a water jump and the 100 m race of outdoor tracks.

During events and concerts, the southern bend of the running track forms an event restaurant, while the straights and the northern bend serve as exhibition and fair storage spaces.

Can you train cycling in the arena?

Yes! The arena's running track was designed together with Kokkola's cyclists, and it is also suitable for road cycling training.

Can you train athletics events in the arena?

Yes, you can! The athletics facilities are located in the north-east corner of the arena. Thanks to them, all athletics events can be trained in the arena.

In addition to facilities for the long jump, high jump, shot put, javelin, hammer and discus, the north-east corner also serves as a batting practice area for pesäpallo (Finnish baseball).

Throwing events such as the hammer, javelin and discus are not possible in competitions, but the arena still offers good conditions for training these events too, for example for throwing practice and supporting exercises. All of these facilities are available for school PE.

The pole vault facility is located inside the arena and can be used during athletics competitions such as the heptathlon. In everyday use, the pole vault facility is under the stands.

Can you play tennis in the arena?

Yes! The tennis hall on the arena's third floor meets the requirements for a club-level training and competition court.

The floor is a surface designed especially for tennis. The hall has a small balcony stand which, besides seating spectators, can serve for example as an archery range when the hall is not otherwise in use.

Golf can also be practised in the hall. In addition to the tennis hall, tennis can also be played in the indoor arena.

Does the arena have a mirror hall? Will there be a dance studio?

A mirror hall of about 290 m² is located on the second floor on the football pitch side of the arena. The mirror hall with its parquet floor is suitable for dance, group exercise, rhythmic gymnastics, ballet, yoga, karate, taekwondo, tai chi and many other activities.

During events, the space can serve for example as an event restaurant or a VIP area.

Can you do artistic gymnastics in the arena?

The artistic gymnastics area on the arena's third floor was designed together with the sport's national federation. The space allows safe artistic gymnastics and gymnastics, and the foam pit in particular is popular with young people.

The space is especially well suited to school PE, as the apparatus is permanently installed, which makes it easier to run PE lessons.

Can you do wall climbing in the arena?

The north-east corner of the arena forms a space almost 16 metres high, which houses the arena's 16-metre-high and 9-metre-wide climbing wall, the top three metres of which form an overhang.

The wall meets climbers' requirements and is a very striking part of the arena's interior architecture.

Can you train martial arts in the arena?

The martial arts area on the second floor of Kokkola Arena offers excellent facilities for wrestling, boxing and mat sports. The area can be combined into one large space for camps and tournaments. The martial arts area has its own changing rooms.

Examples of sports that can be practised in the martial arts facilities:

  • Aikido
  • Brazilian jiu-jitsu
  • Hapkido
  • Judo
  • Jujutsu
  • Archery
  • Karate
  • Kung fu
  • Catch wrestling
  • Boxing
  • Wrestling, freestyle
  • Wrestling, Greco-Roman
  • Kickboxing
  • Taekwondo
  • Tai chi
  • Muay Thai
  • Mixed martial arts
Does the arena have a gym?

The gym is located on the second and third floors and has a separate entrance from Kaarlelankatu at street level.

The gym is run by a separate operator or by Urheilupuisto Oy. The aim of the design has been to locate some of the facilities at street level so that they are easily accessible, for example for senior customers. The strength training area is located on the 3rd floor.

Examples of activities that can be practised in the gym:

  • Weightlifting
  • Powerlifting
  • CrossFit
  • Fitness
  • Bodybuilding
Can you play football at Kokkola Arena?

Yes! Kokkola Arena's football pitch meets the requirements of the Union of European Football Associations (UEFA) category II, which allows international matches and club teams' participation in European competitions.

The football stadium includes a main stand with about 1,200 seats, a stand with about 800 seats opposite the main stand, and end stands.

There are about 2,000 seats in total, of which 25 are designed for people with reduced mobility. The stadium has 1,580 standing places. The stadium also includes maintenance, staff and restaurant facilities, and changing rooms shared with indoor sports.

Examples of sports that can be played on the football pitch:

  • American football
  • Baseball
  • Skiing
  • Football, UEFA category 2 pitch
  • Archery
  • Start and finish area for running events
  • Children's skiing on the pitch
  • Pesäpallo (Finnish baseball)
  • Rugby
  • Sprint skiing on the pitch
  • Snowcross
Why is Kokkola Arena getting a football arena?

Keskuskenttä has reached the end of its life cycle, there are no parking spaces, and the facilities needed for doping control and press conferences are inadequate.

Why will there be no running track around the football pitch?

A running track around the football pitch would leave the spectators too far from the pitch.

Will the football arena have end stands?

Yes, the football pitch will have end stands.

How will you make sure there is free time for individual users too, and not everything is booked by clubs?

A booking system is being designed for Kokkola Sports Park that also takes individual users into account.

Beach volleyball is a growing sport. Why has it not been considered in the plans?

Unfortunately, not every sport, even growing ones, can be included in Kokkola Sports Park within the proposed budget.

Kokkola lacks a winter practice facility for golf. Why has it not been considered?

A winter practice facility for golf has been considered, and its possible implementation will be decided during the design phase.

Have throwing events been considered at all?

The proposal reserves space for throwing events at Kokkola Arena.

Will there be a bowling alley?

A bowling alley is not part of the proposal.

Will there be a long jump facility?

The proposal includes space for a long jump facility. Its exact location will be planned in the development phase.

Why is there no javelin throwing area?

The proposal reserves space for throwing events at Kokkola Arena.

How has shooting been taken into account, as the sport has brought Kokkola a lot of success?

The conditions for shooting will not get worse.

Horse riding is a popular hobby. Why has it not been taken into account?

Accommodating horse riding indoors would restrict the choice of floor material and surface so much that the multipurpose use of the indoor facilities would be too limited.

Why will the ice hall be renovated last?

Besides the ice hall, other sports facilities in Kokkola also need attention. The construction order is largely determined by the schedules of the Regional State Administrative Agency's (AVI) grant applications for sports facilities.

An outdoor artificial ice rink that is an artificial turf pitch in summer. Can you build this?

Freezing an outdoor artificial ice rink requires an enormous amount of energy, so it is not part of the proposed solution.

Why is the Urheilutalo ground-floor hall to be demolished?

The Urheilutalo ground-floor hall no longer meets the requirements of modern sports buildings.

Is it possible to have two tennis courts in the arena?

According to the plans for Kokkola Arena, the arena will have one court designed solely for tennis, with a tennis surface. In addition, tennis can also be played in the multipurpose arena, where there is room for three courts. So in total, up to four courts can be in play at the same time at Kokkola Arena!

Other facilities

Why are there facilities for physiotherapy?

Physiotherapy and sports physicians are needed during large tournaments to look after the health of players and athletes.

Why will the arena have a classroom?

All the facilities in Kokkola Sports Park have been designed for multipurpose use. The teaching facilities also serve as seminar rooms, press rooms and, during concerts, dressing rooms.

Will there be enough parking spaces?

Enough new parking spaces will be built around the proposed Kokkola Sports Park.

What about bicycles?

Enough new parking spaces will be built around the proposed Kokkola Sports Park, including for bicycles.

Can the stands be modified?

In the proposed solution, the hall's stands consist of loose chairs, movable stands, telescopic stands and fixed stands.

Will there be a playground in the area?

The proposal takes children into account in the landscaping of the area.

Will the restaurant be able to serve alcohol in the performance area and on the sports fields?

The operator of a possible restaurant will decide how alcohol service is arranged, in cooperation with Kokkola Sports Park.

How many beds will the hotel have?

The Kokkola Sports Park hotel is only an idea so far, and there are no detailed plans yet.

Why is there a press room?

After big matches, the press often wants to interview players and teams. A press room is needed for this.

Can you get to the changing rooms directly from outside?

In the proposed solution, the changing rooms can be reached from the football pitch via the pitch's access routes.

Can the changing rooms be expanded, for example during home matches?

The proposed solution outlines two changing rooms to be rented to home teams. The structure of the changing rooms will be designed in the development phase.

Will there be a sauna section?

In the proposed solution, the first-team changing rooms have a sauna section.

Will there be a play area for small children?

The children's play area will be planned during the design phase.

Will there be a café near the ice hockey rinks?

In the proposed solution, there is space for a possible café next to the practice ice rinks.

Events

Do the football pitch and stands add value to organising events?

Kokkola Arena is part of the Kokkola Sports and Event Park complex. The various indoor spaces of Kokkola Arena can host events ranging from gatherings of 100 people to concerts of more than 4,000 people.

The football pitch extends Kokkola Arena's facilities outdoors, for example at agricultural and construction exhibitions, where animals and larger machinery can be shown on the football pitch side. The football pitch also makes outdoor activities possible in connection with fairs and seminars.

Outdoor concerts can be held in the Event Park and, if needed, in the football arena. Used together with Kokkola Arena, these make it possible, for example, to hold festivals with one stage indoors. This avoids having to build a separate tent, among other things.

The football pitch is also suitable for open-air concerts of up to about 6,000 people; larger open-air concerts and events can be held in the Event Park.

What kinds of concerts can be held at Kokkola Arena?

Kokkola Arena has many spaces of different sizes that can host concerts for anything from a hundred people to 4,500 people.

As an indoor concert venue, Kokkola Arena offers excellent possibilities. The arena's logistics, stage and restaurant services have been designed to serve concerts for a total of 4,500 visitors.

Kokkola Arena's logistics have been designed so that the set and staging for an event can be built as smoothly and quickly as possible.

What kinds of events can be held at Kokkola Arena?

Kokkola Arena offers excellent conditions as a fair venue. Fairs can be held in the hall area intended for ball games and partly on the running track. The other spaces reserved for sports can stay in use during a fair, or they can be rented for the fair by separate agreement. Access to these spaces has been designed with these options in mind. Restaurant services, the fair kitchen and other rentable commercial premises support fair events, just as they do concerts.

Kokkola Arena meets the requirements of large congresses thanks to its large seating capacity and logistics solutions. Large congresses include, for example, party conferences and corporate events. Smaller meetings and events can be held in the restaurant and other rentable spaces in the shared facilities of Kokkola Arena and the football arena. Multipurpose use is the foundation of the whole operation.

Kokkola Arena's logistics have been designed so that the set and staging for an event can be built as smoothly and quickly as possible. At the northern end of Kokkola Arena there are large doors through which vans can drive into the arena, which makes it easier to build fairs, for example. The weight limit is 3,500 kg. When large events are built, the loading dock and the temporary storage area designed next to it are used, which helps make building and dismantling the event smoother.

What size of concerts can be held in the arena?

The arena's outlined concert capacity is about 4,500 people. More detailed information will be available when the development phase is complete.

How many seats will there be?

The arena's outlined seating capacity is about 3,000 people. More detailed information will be available when the development phase is complete.

Is the sound system good enough for both chamber orchestra and popular music concerts?

Yes, it is.

The event space will be warm, won't it? It's unpleasant to be cold at concerts.

Yes, it is.

Construction phase

When will the design work start?

The design work started in autumn 2022.

When will construction be completed?

Depending on the chosen scope of the project, in 2025–2027.

When will the plans be ready?

The plans for Kokkola Arena were completed in summer 2023.

When will the practice ice rink and the ice hall renovation be designed?

The design of the practice ice rink and the ice hall renovation will start in winter 2023–2024. Join the workshop!

In what order will Kokkola Sports Park be built?

Construction of Kokkola Sports Park starts with the indoor arena of Kokkola Arena. The Urheilutalo extension will be demolished to make way for the football pitch. The demolition will be scheduled for the summer so that the impact on indoor ball sports is as short as possible and the sports can move to Kokkola Arena in late autumn or early winter.

The start of the development and implementation phases of the practice ice rink and the ice hall renovation will be brought for decision during 2023 and 2024. The aim is for the Kokkola Sports Park complex to be in use in 2025 or 2026.

What is the contract area of the project? Does it end four metres from the walls, as rumoured?

For Kokkola Arena, Kokkola Sports Park has leased a plot from the city that ends four metres outside the walls of the hybrid arena.

Are area and street construction, such as car parks and streets, the city's responsibility? If so, how much do they cost?

The city is responsible for area and street construction in Kokkola Sports Park.

Why is Kokkola Sports Park being built as an alliance?

An alliance is ideal for delivering large, complex projects. With an alliance, the project stays within its budget and schedule.

What is an alliance?

An alliance is an equal partnership of companies for the development and implementation of a project, which is jointly responsible for the project's success. https://kokkolaareena.fi/allianssi/

Who is the main contractor of the project?

An alliance has no main contractor.

Who are the members of the alliance?

The architectural firms Uki Arkkitehdit and Jyrki Jääskeläinen, Ramboll Finland, Granlund Pohjanmaa, YIT and Kokkolan Urheilupuisto.

Why does the project have an architect?

Designing a complex sports centre requires expertise. We are also building a building that will remain long after us, and we want it to fit in well in Kokkola.

Why does the project have a structural engineer?

The structural engineer designs the structural solutions based on the architects' drawings so that the building can actually be built.

Will the project exceed its budget and schedule?

Nine out of ten alliances carried out in Finland manage to stay on schedule and come in under budget.

How is construction supervised?

The alliance hires external supervisors to monitor the quality of development and implementation.

Who decides what will be built in Kokkola Sports Park?

The City of Kokkola and the Board of Kokkola Sports Park.

How can I influence what is built in Kokkola Sports Park?

The best way to have an influence is to take part in the development of Kokkola Sports Park through your own sports or cultural club, in discussions and workshops.

Why are there no women working in the alliance?

There are women working in the alliance, but there could be more. Unfortunately, there are few women available for recruitment in the construction industry.

How have environmental issues been taken into account?

Kokkola Sports Park aims to be emission-free and environmentally friendly. Kokkola Sports Park's energy system is based on recycling waste energy, which makes our energy system very environmentally friendly. We will apply for an environmental certificate for Kokkola Arena.

How has accessibility been taken into account?

The sports facility grants we have applied for require that accessibility requirements are met.

How has energy efficiency been taken into account?

Kokkola Sports Park aims to be emission-free and environmentally friendly. Kokkola Sports Park's energy system is based on recycling waste energy, which makes our energy system very environmentally friendly.

How has ventilation been taken into account?

Kokkola Sports Park's HVAC system is designed to meet modern requirements.

Designing Kokkola Arena

Who designed Kokkola Arena?

Kokkola Arena was designed by the architectural firms UKI Arkkitehdit and Jääskeläinen together with about 150 volunteers from Kokkola.

Who designed the football pitch?

Kokkola Arena, the complex formed by the multipurpose arena and the football arena, was designed by the architectural firms UKI Arkkitehdit and Jääskeläinen together with Kokkola's football clubs and city officials.

Who designed the indoor arena?

Kokkola Arena was designed by the architectural firms UKI Arkkitehdit and Jääskeläinen together with Kokkola's volleyball, floorball, martial arts, artistic gymnastics, dance, tennis, golf and athletics clubs, event organisers and city officials.

What is the wow factor of Kokkola Arena?

It is good to remember that the wow factor is subjective. What wows one person may leave another indifferent.

Building an interesting place for sports, meeting and events requires investment in visual appearance, architecture, AV technology and energy systems. There have been no compromises on these: the architecture of Kokkola Arena is striking and supports the urban architecture of the area.

The AV technology at Kokkola Arena is modern and fit for purpose. Kokkola Sports Park's energy system is innovative even on a global scale and has been awarded an increased sports facility grant by the Ministry of Education and Culture.

The Kokkola Arena restaurant offers unprecedented views of both the football pitch and the indoor sports hall at the same time.

The climbing wall, which runs through four floors and curves inwards over its last three metres, is a striking architectural detail in an arena that is impressive in every way.

Costs of Kokkola Arena

How much will Kokkola Sports Park cost?

The City of Kokkola proposes a budget of at most 74.9 million euros for building Kokkola Sports Park.

How much will building Kokkola Sports Park raise Kokkola's tax rate?

The development and implementation of Kokkola Sports Park are financed with external loan financing on the company's balance sheet, which does not directly burden the city's finances. Indirectly, the project will lower the tax rate as Kokkola Sports Park attracts more taxpayers to Kokkola.

Will the fees for sports services go up?

The fees for sports services will remain reasonable.

Has the project found private funding?

Negotiations on bringing in private money have mainly concerned selling the naming rights of the arena. The return expectations of private capital are currently higher than those of loan financing, so using it would raise operating costs.

Who pays the project's 74.9 million?

The loan is financed by an external financial institution. Urheilupuisto Oy repays the loan with income from its operations and possible external capitalisation.

What are the arena's operating costs and income?

The operating budget is based on the following assumptions:

Budgeted expenses:
Loan interest and repayments, maintenance of the pitches and facilities, and other costs: €4.5M

Budgeted income:
User fees, the city's service purchases and facility rents: €4.9M

What are the hourly rates for, for example, the indoor facilities or the football pitch?

The usage prices of Kokkola Arena's indoor facilities are in line with similar sports and event arenas in Finland. In addition, the pricing supports exercise for children and young people under 18.

For example, the fee for one indoor court will be about €20–60/h depending on the event and the time of day, and the fees for the football pitch will be about €40–60/h depending on the event and the time of day.

The prices will be reviewed once the actual utilisation rates of Kokkola Arena are known. It is in the company's interest to price the use of the arena so that it is full every evening.

What is the cost structure of the project so far?

Up to summer 2023, the company has used funds for recruiting the CEO, visiting reference sites, interviewing stakeholders, tendering expert services and the alliance, project and budget planning for the whole Kokkola Sports Park, organising user workshops, architectural design of Kokkola Arena, structural design of Kokkola Arena, building services design of Kokkola Arena, implementation planning of Kokkola Arena, validation of the plans, communications, information and project administration.

How much money has been spent so far?

The budget for the project development and budgeting phase KAS0 of the whole Kokkola Sports Park, i.e. the complex formed by Kokkola Arena, the practice ice rink and the ice hall renovation, which ended in summer 2022, was €991,943 and the actual cost was €977,671. The budget for the development phase KAS1 of Kokkola Arena was 2.8 million euros, and the actual cost in summer 2023 is 1.5 million euros. In total, the company had used 2.5 million euros by summer 2023.

How much of Kokkola Arena's target cost of about 56.5 million is the indoor arena's share?

The target cost of the indoor arena is 51.7 million euros.

How much of the total cost of about 56 million is now the football arena's share?

The target cost of the football pitch is 4.8 million euros.